MB5-858 · Question #86

You need to create 3 project management diamond. Which constraints should you use at each corner?

The correct answer is D. cost, quality, scope, time. See the full explanation below for the reasoning.

Question

You need to create 3 project management diamond. Which constraints should you use at each corner?

Options

  • Acost, quality, scope, risk
  • Bexpectations, scope, time, risk
  • Ccost, expectations, scope, time
  • Dcost, quality, scope, time

How the community answered

(45 responses)
  • A
    13% (6)
  • B
    2% (1)
  • C
    4% (2)
  • D
    80% (36)