MB5-858 · Question #104
You are a project manager for Contoso Ltd, an e-commerce company. Contoso's Microsoft Dynamics implementation project is in the deployment phase, and you are planning the user acceptance testing…
The correct answer is D. testing the end-to-end system to ensure the system supports the company's transactions. See the full explanation below for the reasoning.
Question
You are a project manager for Contoso Ltd, an e-commerce company. Contoso's Microsoft Dynamics implementation project is in the deployment phase, and you are planning the user acceptance testing. Which action should be the focus of the testing?
Options
- Atesting the performance to ensure the system can handle the predicted peak time transaction volumes
- Btesting that the system supports the company's transaction data
- Ctesting data migration
- Dtesting the end-to-end system to ensure the system supports the company's transactions
How the community answered
(64 responses)- A3% (2)
- B13% (8)
- C6% (4)
- D78% (50)