You are a project manager for a Microsoft Dynamics implementation. The project is in the deployment phase, and you are planning the final data migration to production. You need to split the effort…

The correct answer is B. one week. See the full explanation below for the reasoning.

Question

You are a project manager for a Microsoft Dynamics implementation. The project is in the deployment phase, and you are planning the final data migration to production. You need to split the effort into two phases: phase one and phase two. How much time should you typically plan between phase one and phase two?

Options

  • Aone day
  • Bone week
  • Ctwo weeks
  • Done month

How the community answered

(56 responses)
  • A
    5% (3)
  • B
    82% (46)
  • C
    2% (1)
  • D
    11% (6)

Community Discussion

No community discussion yet for this question.