Which activity may be included in project closure?
The correct answer is A. Provide additional user training. See the full explanation below for the reasoning.
Question
Which activity may be included in project closure?
Options
- AProvide additional user training.
- BEstablish ongoing quality and testing strategy.
- CConduct a disaster recovery test.
- DReview the scope and change requests.
How the community answered
(32 responses)- A75% (24)
- B6% (2)
- C3% (1)
- D16% (5)