MB-335 · Question #84
A company uses Dynamics 365 Supply Chain Management. A piece of machinery that is critical to a production order breaks down during a production order. The completed quantities of the production…
The correct answer is D. End the current production order and create a new order for the remaining quantity. You've hit your limit · resets 4am (America/New_York)
Implement production methods
Question
A company uses Dynamics 365 Supply Chain Management. A piece of machinery that is critical to a production order breaks down during a production order. The completed quantities of the production order must be shipped. The remaining quantity on the production order needs to be completed once the machinery is fixed. Negative inventory is not allowed for the items. You need to resolve the production issue. What should you do?
Options
- AShip the production quantity that is reported as finished.
- BCancel the production order and create a new order for the finished quantity.
- CSplit the current production order into two production orders.
- DEnd the current production order and create a new order for the remaining quantity
How the community answered
(52 responses)- A8% (4)
- B4% (2)
- C17% (9)
- D71% (37)
Explanation
You've hit your limit · resets 4am (America/New_York)
Topics
#production order management#end production order#split production order#machinery breakdown
Community Discussion
No community discussion yet for this question.