MB-335 · Question #83

MB-335 Question #83: Real Exam Question with Answer & Explanation

Sign in or unlock MB-335 to reveal the answer and full explanation for question #83. The question stem and answer options stay visible for context.

Question

A customer produces light projection toys for holiday decorations throughout the year. You are in the first month of a season. Production flows take one day to complete. The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs. You need to plan the jobs to be completed two weeks prior to the start of the next season. What are two possible ways to achieve this goal? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.

Options

  • ASet the Automatic planning option for each unscheduled job to Yes.
  • BManually schedule each unscheduled job forward from the date of the end of the season.
  • CManually schedule each unscheduled job to the previous period of the end of the next season.
  • DSet the Automatic planning option for each unscheduled job to No.
  • EManually schedule each unscheduled job on its due date.
  • FManually schedule each unscheduled job to the next period of the start of the next season.