A Discrete manufacturing company produces speakers. The high-end speaker model uses protective rubber strips on the edges. Approximately five inches of rubber is consistently scrapped in the…

The correct answer is A. Set a Constant scrap of five on the BOM line for rubber. You've hit your limit · resets 4am (America/New_York)

Configure products

Question

A Discrete manufacturing company produces speakers. The high-end speaker model uses protective rubber strips on the edges. Approximately five inches of rubber is consistently scrapped in the production process, regardless of production quantity. Workers manually consume the extra material on the picking list or scrap it in an inventory journal. You need configure the system to automatically account for this scrap on the Bill of materials (BOM). What should you do?

Options

  • ASet a Constant scrap of five on the BOM line for rubber.
  • BAdd an additional BOM line for five inches and set consumption to Variable.
  • CSet a Variable scrap of five percent for the rubber BOM line.
  • DIncrease the required quantity of the rubber component by five on the BOM.

How the community answered

(31 responses)
  • A
    81% (25)
  • B
    13% (4)
  • C
    3% (1)
  • D
    3% (1)

Explanation

You've hit your limit · resets 4am (America/New_York)

Topics

#BOM configuration#constant scrap#material consumption#scrap accounting

Community Discussion

No community discussion yet for this question.

Full MB-335 Practice