A company uses the built-in Dynamics 365 Supply Chain Management master planning engine. Planned orders are automatically firming and are firmed during the current week. You need to reconfigure the…

The correct answer is A. firming time fence to one week. https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/planned-order-firming

Implement master planning

Question

A company uses the built-in Dynamics 365 Supply Chain Management master planning engine. Planned orders are automatically firming and are firmed during the current week. You need to reconfigure the system for the new Planning Optimization master planning engine. What should you change?

Options

  • Afirming time fence to one week
  • Bfirming time fence to lead-time plus one week
  • Copen orders' firming date to be the requirement date
  • Dfirming time fence to be longer than the lead time
  • Efirming time fence to 0

How the community answered

(37 responses)
  • A
    84% (31)
  • C
    5% (2)
  • D
    8% (3)
  • E
    3% (1)

Explanation

https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning- optimization/planned-order-firming