MB-320 · Question #56
You are responsible for product and formula maintenance for a paint manufacturer. You create a formula for white paint and add its lines. When the formula size increases or an ingredient changes…
The correct answer is C. Scalable. https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production- control/formulas-versions#use-the-scalable-feature
Configure measures and segments
Question
You are responsible for product and formula maintenance for a paint manufacturer. You create a formula for white paint and add its lines. When the formula size increases or an ingredient changes, the quantity of the pigment ingredient must be adjusted proportionately. You need to set up the formula line for the pigment. Which formula feature should you use?
Options
- APegged supply
- BStep consumption
- CScalable
- DVariable
How the community answered
(38 responses)- A8% (3)
- B18% (7)
- C71% (27)
- D3% (1)
Explanation
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production- control/formulas-versions#use-the-scalable-feature
Topics
#formula lines#scalable formula#process manufacturing#ingredient adjustment