nerdexam
Microsoft

MB-320 · Question #59

You are building the Bill of materials (BOM) for a new production item. The new item has a subcomponent. Subproduction orders for the subcomponent must be created when estimating production orders…

The correct answer is D. Pegged supply. https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production- control/bill-of-material-bom

Configure measures and segments

Question

You are building the Bill of materials (BOM) for a new production item. The new item has a subcomponent. Subproduction orders for the subcomponent must be created when estimating production orders. You need to configure the BOM line to generate subproduction orders. Which BOM line type should you use?

Options

  • APhantom
  • BVendor
  • CItem
  • DPegged supply

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    14% (3)
  • D
    77% (17)

Explanation

https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production- control/bill-of-material-bom

Topics

#BOM line types#pegged supply#subproduction orders#production BOM

Community Discussion

No community discussion yet for this question.

Full MB-320 Practice