A company produces pipe at certain fixed lengths. The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the…
The correct answer is B. Build capability related to length and assign to the appropriate resources. https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define- resource-capabilities
Configure measures and segments
Question
A company produces pipe at certain fixed lengths. The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this. You need to configure the resources to account for these different products. What should you do?
Options
- AConfigure the Data/Hour option on the Capacity unit field on the resource.
- BBuild capability related to length and assign to the appropriate resources.
- CCreate a resource group for each length.
- DCreate a resource for each length.
How the community answered
(43 responses)- A16% (7)
- B72% (31)
- C7% (3)
- D5% (2)
Explanation
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define- resource-capabilities
Topics
#resource capabilities#machine scheduling#production resources#capability assignment