MB-320 · Question #57

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup: - The setup uses a Lean schedule group with a throughput…

The correct answer is B. Create a route with a runtime =1, a process quantity =10, and the operation's hours/time =1. See the full explanation below for the reasoning.

Question

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup: - The setup uses a Lean schedule group with a throughput ratio=2 - The process activity tied to production flow has the following runtime activity times: time=3 min, per quantity=1 - The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8- hour day) - The throughput is 10 per hour You need to set up a Discrete operation to mirror the item's production flow activity. What should you do?

Options

  • ACreate a route with a runtime =1, a process quantity =6, and the operation's hours/time =1
  • BCreate a route with a runtime =1, a process quantity =10, and the operation's hours/time =1
  • CCreate a route with a runtime =6, a process quantity =1, and the operation's hours/time =1
  • DCreate a route with a runtime =10, a process quantity =6, and the operation's hours/time =1

How the community answered

(46 responses)
  • A
    11% (5)
  • B
    80% (37)
  • C
    2% (1)
  • D
    7% (3)