Microsoft
MB-320 · Question #57
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup: - The setup uses a Lean schedule group with a throughput…
The correct answer is B. Create a route with a runtime =1, a process quantity =10, and the operation's hours/time =1. See the full explanation below for the reasoning.
Question
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup: - The setup uses a Lean schedule group with a throughput ratio=2 - The process activity tied to production flow has the following runtime activity times: time=3 min, per quantity=1 - The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8- hour day) - The throughput is 10 per hour You need to set up a Discrete operation to mirror the item's production flow activity. What should you do?
Options
- ACreate a route with a runtime =1, a process quantity =6, and the operation's hours/time =1
- BCreate a route with a runtime =1, a process quantity =10, and the operation's hours/time =1
- CCreate a route with a runtime =6, a process quantity =1, and the operation's hours/time =1
- DCreate a route with a runtime =10, a process quantity =6, and the operation's hours/time =1
How the community answered
(46 responses)- A11% (5)
- B80% (37)
- C2% (1)
- D7% (3)
Community Discussion