MB-240 · Question #124

You are a dispatcher for Dynamics 365 Field Service. You schedule a resource to a work order using the schedule board. The resource appears available, but informs you they put in a Time Off Request…

The correct answer is C. Time off request has not been approved D. The time zone for the resource is set incorrectly. See the full explanation below for the reasoning.

Question

You are a dispatcher for Dynamics 365 Field Service. You schedule a resource to a work order using the schedule board. The resource appears available, but informs you they put in a Time Off Request for that period. Which two options are potential reasons why the resource appears available, but informs you they are not available? Each answer represents a complete solution.

Options

  • AThe schedule board is not syncing with the resource's schedule
  • BTime off request is Inactive
  • CTime off request has not been approved
  • DThe time zone for the resource is set incorrectly

How the community answered

(46 responses)
  • A
    9% (4)
  • B
    17% (8)
  • C
    74% (34)