A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response. Which of the following is the BEST…

The correct answer is A. Document the new risks and continue the Plan Risk Responses process. You've hit your session limit · resets 10:20pm (America/New_York)

Risk Management

Question

A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response. Which of the following is the BEST thing for the project manager to do?

Options

  • ADocument the new risks and continue the Plan Risk Responses process.
  • BMake sure the project work is better understood.
  • CSpend more time making sure the risk responses are clearly defined.
  • DGet more people involved in the Identify Risks process since risks have been missed.

How the community answered

(39 responses)
  • A
    82% (32)
  • B
    3% (1)
  • C
    10% (4)
  • D
    5% (2)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#secondary risks#risk response planning#residual risks#risk identification