Which of the following techniques incorporates a form of risk assessment?

The correct answer is D. Three-point estimating. You've hit your session limit · resets 10:20pm (America/New_York)

Risk Management

Question

Which of the following techniques incorporates a form of risk assessment?

Options

  • AArrow diagramming method
  • BNetwork diagramming
  • CCritical path method
  • DThree-point estimating

How the community answered

(52 responses)
  • A
    15% (8)
  • B
    4% (2)
  • C
    8% (4)
  • D
    73% (38)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#three-point estimating#risk assessment#PERT#schedule estimation