A Project with a total funding of $70,000 finished with a BAC value of $60,000. What term can best describe the difference of $10,000? ISEB ISEB-PM1 Exam
The correct answer is A. Management Contingency Reserve. You've hit your weekly limit · resets 5am (America/New_York)
Project Control
Question
A Project with a total funding of $70,000 finished with a BAC value of $60,000. What term can best describe the difference of $10,000? ISEB ISEB-PM1 Exam
Options
- AManagement Contingency Reserve
- BCost Variance
- CSchedule Variance
- DManagement Overhead
How the community answered
(53 responses)- A75% (40)
- B13% (7)
- C8% (4)
- D4% (2)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#management reserve#BAC#budget at completion#contingency