A Project with a total funding of $70,000 finished with a BAC value of $60,000. What term can best describe the difference of $10,000? ISEB ISEB-PM1 Exam

The correct answer is A. Management Contingency Reserve. You've hit your weekly limit · resets 5am (America/New_York)

Project Control

Question

A Project with a total funding of $70,000 finished with a BAC value of $60,000. What term can best describe the difference of $10,000? ISEB ISEB-PM1 Exam

Options

  • AManagement Contingency Reserve
  • BCost Variance
  • CSchedule Variance
  • DManagement Overhead

How the community answered

(53 responses)
  • A
    75% (40)
  • B
    13% (7)
  • C
    8% (4)
  • D
    4% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#management reserve#BAC#budget at completion#contingency