ISEB-PM1 · Question #556

Reserve Analysis a technique not used in:

The correct answer is C. Control Costs. You've hit your weekly limit · resets 5am (America/New_York)

Project Control

Question

Reserve Analysis a technique not used in:

Options

  • AEstimate Costs
  • BEstimating Activity Duration
  • CControl Costs
  • DDetermine Budget

How the community answered

(39 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    82% (32)
  • D
    10% (4)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#reserve analysis#cost estimating#cost control#contingency reserve