ISEB-PM1 · Question #447
What should a project manager do with low-priority risks? ISEB ISEB-PM1 Exam
The correct answer is B. Monitor periodically with other low-priority risks. Monitoring low-priority risks periodically is the correct approach because these risks don't warrant immediate action or significant resources, but ignoring them entirely could allow conditions to change and elevate their impact - periodic review keeps them on the radar without…
Question
What should a project manager do with low-priority risks? ISEB ISEB-PM1 Exam
Options
- AIgnore low-priority risks
- BMonitor periodically with other low-priority risks
- CCreate a mitigation plan for the low-priority risks
- DIncrease the contingency reserve
How the community answered
(25 responses)- A12% (3)
- B80% (20)
- C4% (1)
- D4% (1)
Explanation
Monitoring low-priority risks periodically is the correct approach because these risks don't warrant immediate action or significant resources, but ignoring them entirely could allow conditions to change and elevate their impact - periodic review keeps them on the radar without over-investing in them.
Why the distractors are wrong:
- A (Ignore them): Never appropriate in risk management; risk status changes over time, and today's low-priority risk can become tomorrow's critical issue.
- C (Create a mitigation plan): Mitigation plans are reserved for high-priority risks; applying them to low-priority risks wastes resources that should be allocated elsewhere.
- D (Increase contingency reserve): Contingency reserves address identified risks broadly, but simply increasing reserves doesn't manage low-priority risks - it's also disproportionate to their threat level.
Memory tip: Think of low-priority risks like background apps on your phone - you don't close them, but you check them occasionally to make sure they aren't draining your battery. "Watch but don't act" = periodic monitoring.