ISEB-PM1 · Question #441
Reserve analysis is a tool and technique used in which of the following processes?
The correct answer is A. Monitor and Control Risks. Reserve Analysis is a tool and technique in the Monitor and Control Risks process (Option A), where it is used to compare remaining contingency reserves-both schedule and cost-against the amount of risk still present on the project, ensuring adequate buffer exists to cover…
Question
Reserve analysis is a tool and technique used in which of the following processes?
Options
- AMonitor and Control Risks
- BQualitative Risk Analysis
- CQuantitative Risk Analysis
- DPlan Risk Responses
How the community answered
(42 responses)- A79% (33)
- B2% (1)
- C12% (5)
- D7% (3)
Explanation
Reserve Analysis is a tool and technique in the Monitor and Control Risks process (Option A), where it is used to compare remaining contingency reserves-both schedule and cost-against the amount of risk still present on the project, ensuring adequate buffer exists to cover outstanding threats.
Why the distractors are wrong:
- B (Qualitative Risk Analysis) uses tools like the probability/impact matrix and risk urgency assessment to prioritize risks-not reserve analysis.
- C (Quantitative Risk Analysis) relies on techniques like Monte Carlo simulation, expected monetary value (EMV), and sensitivity analysis to numerically model risk-not reserve analysis.
- D (Plan Risk Responses) focuses on developing response strategies (avoid, mitigate, transfer, accept) for identified risks-not evaluating reserve adequacy.
Memory tip: Link "reserve" to "review" - you review your reserves during monitoring to see if your safety net is still big enough. Reserve Analysis belongs in the controlling phase, not the planning or analysis phases.