Which of the following risk management processes uses brainstorming as a technique?
The correct answer is A. Identify Risks. Identify Risks (A) is correct because it is the process where the project team actively discovers and documents potential risks - and brainstorming is one of its primary information-gathering techniques, explicitly listed in the PMBOK Guide as a tool for this process. Why the…
Question
Which of the following risk management processes uses brainstorming as a technique?
Options
- AIdentify Risks
- BMonitor and Control Risks
- CPlan Risk Management
- DPlan Risk Responses
How the community answered
(47 responses)- A79% (37)
- B2% (1)
- C6% (3)
- D13% (6)
Explanation
Identify Risks (A) is correct because it is the process where the project team actively discovers and documents potential risks - and brainstorming is one of its primary information-gathering techniques, explicitly listed in the PMBOK Guide as a tool for this process.
Why the distractors are wrong:
- B (Monitor and Control Risks) focuses on tracking identified risks, evaluating risk responses, and watching for new risks using tools like risk audits and variance analysis - not creative ideation techniques like brainstorming.
- C (Plan Risk Management) defines how risk activities will be conducted (roles, budget, methodology) - it's about structuring the approach, not discovering risks.
- D (Plan Risk Responses) develops strategies to address already-identified risks (avoid, transfer, mitigate, accept) - the risks are known at this point, so discovery techniques aren't used.
Memory tip: Think of "Identify" as the detective phase - you need creative, generative techniques like brainstorming, Delphi, and interviews to find what could go wrong. All other risk processes assume the risks are already on the list.