ISEB-PM1 · Question #426
Which of the following is an output of the Estimate Activity Resources process?
The correct answer is C. Resource breakdown structure. Resource Breakdown Structure (C) is an output of the Estimate Activity Resources process because it is a hierarchical chart showing the types and categories of resources identified during the estimation process - it is produced as a result of the process, not used as an input…
Question
Which of the following is an output of the Estimate Activity Resources process?
Options
- AAlternative analysis
- BBottom-up estimating
- CResource breakdown structure
- DEnterprise environmental factors
How the community answered
(47 responses)- A6% (3)
- B15% (7)
- C74% (35)
- D4% (2)
Explanation
Resource Breakdown Structure (C) is an output of the Estimate Activity Resources process because it is a hierarchical chart showing the types and categories of resources identified during the estimation process - it is produced as a result of the process, not used as an input or tool.
Why the distractors are wrong:
- A. Alternative analysis is a tool and technique of this process (used to evaluate different resource options), not an output.
- B. Bottom-up estimating is also a tool and technique - a method for estimating by rolling up detailed-level estimates, not something the process produces.
- D. Enterprise environmental factors are inputs to many processes, including this one; they represent organizational context that exists before the process begins.
Memory tip: Think of the acronym RIOT - if it's a Result of doing the work, it's an Output. The Resource Breakdown Structure is a document you create by doing the estimating, while analysis methods and environmental factors are things you use or consult going in. Any time you see a tangible structured document (breakdown structure, register, plan), it's almost always an output.
Topics
Community Discussion
No community discussion yet for this question.