Which of the following is an input to the Qualitative Risk Analysis process?

The correct answer is A. Risk register. ISEB ISEB-PM1 Exam

Risk Management

Question

Which of the following is an input to the Qualitative Risk Analysis process?

Options

  • ARisk register
  • BRisk data quality assessment
  • CRisk categorization
  • DRisk urgency

How the community answered

(41 responses)
  • A
    83% (34)
  • B
    2% (1)
  • C
    10% (4)
  • D
    5% (2)

Explanation

ISEB ISEB-PM1 Exam

Topics

#qualitative risk analysis#risk register#risk inputs#risk assessment