ICYB · Question #145

At the start of a project we are told to "walk the process" from beginning to the end. We do this to_____________________.

The correct answer is B. Draft a Process Map. "Walking the process" (also called a gemba walk in Lean methodology) is a structured observation technique used to understand how work actually flows from start to finish - and the primary output of that walk is a Process Map (B), a visual diagram of each step, decision point…

Define

Question

At the start of a project we are told to "walk the process" from beginning to the end. We do this to_____________________.

Options

  • AMeet the workers
  • BDraft a Process Map
  • CSee what inventory is involved
  • DCheck the repair stations

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    93% (43)
  • C
    4% (2)

Explanation

"Walking the process" (also called a gemba walk in Lean methodology) is a structured observation technique used to understand how work actually flows from start to finish - and the primary output of that walk is a Process Map (B), a visual diagram of each step, decision point, and handoff in the workflow.

  • A (Meet the workers) is wrong because while you may interact with workers during the walk, the purpose isn't social - it's documentation.
  • C (See what inventory is involved) is partially true (inventory is one thing you might notice), but it's too narrow; a Process Map captures the full flow, not just inventory.
  • D (Check the repair stations) is wrong because this implies you're looking for defects specifically, not mapping the end-to-end process.

Memory tip: Think of "walking the process" like retracing a route so you can draw a map - you walk it to map it. Process Walk = Process Map.

Topics

#gemba walk#process mapping#project initiation#Define phase