A project charter typically includes:

The correct answer is C. Business case. A project charter is a foundational document that formally authorizes a project and provides the high-level information needed to initiate it - the business case (option C) is a core component, as it justifies why the project exists by outlining the problem, opportunity, and…

Define

Question

A project charter typically includes:

Options

  • AControl charts
  • BFishbone diagram
  • CBusiness case
  • DStatistical tests

How the community answered

(50 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    92% (46)
  • D
    4% (2)

Explanation

A project charter is a foundational document that formally authorizes a project and provides the high-level information needed to initiate it - the business case (option C) is a core component, as it justifies why the project exists by outlining the problem, opportunity, and expected benefits.

Why the distractors are wrong:

  • A. Control charts - these are quality control tools used during project monitoring/controlling to track process stability over time, not project initiation documents.
  • B. Fishbone diagram - also called an Ishikawa or cause-and-effect diagram, this is a root cause analysis tool used in quality management or problem-solving, not charter creation.
  • D. Statistical tests - these belong to quality analysis and data-driven decision-making phases, far removed from the charter's purpose.

Memory tip: Think of the project charter as the project's birth certificate - it needs a reason for existing (business case), a name (project title), and authority behind it (sponsor signature). If a tool sounds analytical or graphical (charts, diagrams, tests), it belongs later in the project lifecycle, not in the charter.

Topics

#project charter#business case#Define phase#project scope