ICYB · Question #118
A project charter typically includes:
The correct answer is C. Business case. A project charter is a foundational document that formally authorizes a project and provides the high-level information needed to initiate it - the business case (option C) is a core component, as it justifies why the project exists by outlining the problem, opportunity, and…
Question
A project charter typically includes:
Options
- AControl charts
- BFishbone diagram
- CBusiness case
- DStatistical tests
How the community answered
(50 responses)- A2% (1)
- B2% (1)
- C92% (46)
- D4% (2)
Explanation
A project charter is a foundational document that formally authorizes a project and provides the high-level information needed to initiate it - the business case (option C) is a core component, as it justifies why the project exists by outlining the problem, opportunity, and expected benefits.
Why the distractors are wrong:
- A. Control charts - these are quality control tools used during project monitoring/controlling to track process stability over time, not project initiation documents.
- B. Fishbone diagram - also called an Ishikawa or cause-and-effect diagram, this is a root cause analysis tool used in quality management or problem-solving, not charter creation.
- D. Statistical tests - these belong to quality analysis and data-driven decision-making phases, far removed from the charter's purpose.
Memory tip: Think of the project charter as the project's birth certificate - it needs a reason for existing (business case), a name (project title), and authority behind it (sponsor signature). If a tool sounds analytical or graphical (charts, diagrams, tests), it belongs later in the project lifecycle, not in the charter.
Topics