ICYB · Question #102
Which metric is used to evaluate process capability relative to specification limits?
The correct answer is B. Cpk. Cpk (Process Capability Index) directly measures how well a process fits within its specification limits by comparing the process spread and centering to the upper and lower spec limits - making it the standard metric for evaluating process capability. A (RTY – Rolled…
Question
Which metric is used to evaluate process capability relative to specification limits?
Options
- ARTY
- BCpk
- CDPMO
- DTakt time
How the community answered
(49 responses)- A6% (3)
- B88% (43)
- C2% (1)
- D4% (2)
Explanation
Cpk (Process Capability Index) directly measures how well a process fits within its specification limits by comparing the process spread and centering to the upper and lower spec limits - making it the standard metric for evaluating process capability.
- A (RTY – Rolled Throughput Yield) measures the probability that a unit passes through all process steps without defects; it evaluates quality flow, not spec limit compliance.
- C (DPMO – Defects Per Million Opportunities) quantifies defect frequency at scale (used in Six Sigma sigma-level calculations) but doesn't directly reference specification limits in a capability ratio.
- D (Takt time) is a lean/flow metric that sets the production rate needed to meet customer demand - entirely unrelated to specification limits.
Memory tip: Think of the "k" in Cpk as "keeps it centered" - Cpk penalizes a process that drifts off-center relative to the spec limits, which is exactly what capability analysis is designed to catch.