In which technique are phases overlapped that would normally be done in sequence?
The correct answer is C. Fast tracking. Fast tracking is a schedule compression technique that runs project phases simultaneously rather than sequentially to shorten the overall duration.
Question
In which technique are phases overlapped that would normally be done in sequence?
Options
- ACritical path
- BLead time
- CFast tracking
- DProject tracking
How the community answered
(30 responses)- A7% (2)
- B3% (1)
- C90% (27)
Why each option
Fast tracking is a schedule compression technique that runs project phases simultaneously rather than sequentially to shorten the overall duration.
Critical path is a method for identifying the longest sequence of dependent tasks that determines the minimum project duration, not a technique for overlapping phases.
Lead time refers to starting a successor activity before its predecessor finishes, which is a scheduling relationship - fast tracking describes the broader strategy of overlapping entire phases.
Fast tracking deliberately overlaps phases or activities that would normally be performed in sequence, such as beginning construction before design is fully complete. This compresses the schedule but introduces increased risk because later phases may need rework if earlier phases change.
Project tracking is a monitoring and controlling activity, not a schedule compression technique.
Concept tested: Fast tracking schedule compression technique