In which technique are phases overlapped that would normally be done in sequence?

The correct answer is C. Fast tracking. Fast tracking is a schedule compression technique that runs project phases simultaneously rather than sequentially to shorten the overall duration.

Security Program Management & Governance

Question

In which technique are phases overlapped that would normally be done in sequence?

Options

  • ACritical path
  • BLead time
  • CFast tracking
  • DProject tracking

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    3% (1)
  • C
    90% (27)

Why each option

Fast tracking is a schedule compression technique that runs project phases simultaneously rather than sequentially to shorten the overall duration.

ACritical path

Critical path is a method for identifying the longest sequence of dependent tasks that determines the minimum project duration, not a technique for overlapping phases.

BLead time

Lead time refers to starting a successor activity before its predecessor finishes, which is a scheduling relationship - fast tracking describes the broader strategy of overlapping entire phases.

CFast trackingCorrect

Fast tracking deliberately overlaps phases or activities that would normally be performed in sequence, such as beginning construction before design is fully complete. This compresses the schedule but introduces increased risk because later phases may need rework if earlier phases change.

DProject tracking

Project tracking is a monitoring and controlling activity, not a schedule compression technique.

Concept tested: Fast tracking schedule compression technique

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#fast tracking#schedule compression#project management#phase overlap

Community Discussion

No community discussion yet for this question.

Full GSLC Practice