GSLC · Question #322
All of the following are the outputs of the Acquire Project Team process except for which one?
The correct answer is B. Enterprise environmental factors. The Acquire Project Team process in PMBOK has defined outputs. Enterprise environmental factors are inputs to this process, not outputs.
Question
All of the following are the outputs of the Acquire Project Team process except for which one?
Options
- AResource calendars
- BEnterprise environmental factors
- CProject staff assignments
- DProject management plan updates
How the community answered
(58 responses)- A2% (1)
- B91% (53)
- C2% (1)
- D5% (3)
Why each option
The Acquire Project Team process in PMBOK has defined outputs. Enterprise environmental factors are inputs to this process, not outputs.
Resource calendars are a valid output, documenting the time periods during which acquired team members are available.
Enterprise environmental factors - such as organizational policies, market conditions, and existing HR systems - serve as inputs that constrain or influence the Acquire Project Team process. They are pre-existing conditions the project must work within, and cannot be produced as an output of this process.
Project staff assignments are a valid output, listing the people assigned to the project and their roles.
Project management plan updates are a valid output, reflecting changes such as a staffing management plan revision.
Concept tested: PMBOK Acquire Project Team process inputs and outputs
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.