Question
Tim is working as a project manager for the TCH project. The project is in the final stages and the closing processes are being performed. He has prepared the lessons learned document. This document will be the part of ____.
Options
- AThe project's performance record
- BThe project charter
- CThe risk register
- DThe company's organizational process assets