Question

Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

Options

  • AProject Management Information System
  • BChange Control System
  • CIntegrated Change Control System
  • DQuality Management System

Unlock GSLC to see the answer

You've previewed enough free GSLC questions. Unlock GSLC for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full GSLC Practice