GSLC · Question #128

Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for…

The correct answer is A. Project Management Information System. The Project Management Information System (PMIS) is the overarching parent system that contains the Change Control System as a subsystem. It provides the full infrastructure for storing, retrieving, and distributing project information.

Security Program Management & Governance

Question

Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

Options

  • AProject Management Information System
  • BChange Control System
  • CIntegrated Change Control System
  • DQuality Management System

How the community answered

(28 responses)
  • A
    89% (25)
  • B
    4% (1)
  • C
    7% (2)

Why each option

The Project Management Information System (PMIS) is the overarching parent system that contains the Change Control System as a subsystem. It provides the full infrastructure for storing, retrieving, and distributing project information.

AProject Management Information SystemCorrect

According to PMBOK, the PMIS is the parent system that encompasses subsidiary systems including the Change Control System; it provides the organizational tools and processes for managing all project information, including the tracking and approval workflows that make up the Change Control System Donna is documenting.

BChange Control System

The Change Control System is the system Donna is documenting inside her plan - it is the child subsystem being described, not the parent that contains it.

CIntegrated Change Control System

Integrated Change Control is a process (one of the ten project integration management processes) that describes how changes are reviewed and approved, not a named system that serves as a parent to the Change Control System.

DQuality Management System

The Quality Management System governs quality planning, assurance, and control activities and is a separate knowledge area that does not serve as the parent of the Change Control System.

Concept tested: PMIS as parent system of the Change Control System

Topics

#change control#PMIS#project management#change management plan