nerdexam
GIAC

GSLC · Question #127

GSLC Question #127: Real Exam Question with Answer & Explanation

Sign in or unlock GSLC to reveal the answer and full explanation for question #127. The question stem and answer options stay visible for context.

Question

Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid configuration management activities except for which one?

Options

  • AConfiguration Identification
  • BConfiguration Item Costing
  • CConfiguration Status Accounting
  • DConfiguration Verification and Auditing

Unlock GSLC to see the answer

You've previewed enough free GSLC questions. Unlock GSLC for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full GSLC Practice