You are compiling and reviewing the comments to draft deliverables prior to forwarding them to the contractor for incorporation into the final draft. You are responsible for communicating the…
The correct answer is A. Contractor. See the full explanation below for the reasoning.
Question
You are compiling and reviewing the comments to draft deliverables prior to forwarding them to the contractor for incorporation into the final draft. You are responsible for communicating the changes to the reviewer who initially made the comments. Who among the following will be responsible for updating the draft deliverables and producing the final deliverables in the above scenario?
Options
- AContractor
- BProject manager
- CReviewer
- DRisk manager
How the community answered
(39 responses)- A82% (32)
- B3% (1)
- C5% (2)
- D10% (4)
Community Discussion