GCPM · Question #88

Which of the following are inputs of the Develop project team process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is A. Project management plan C. Project staff assignment D. Resource calendar. See the full explanation below for the reasoning.

Question

Which of the following are inputs of the Develop project team process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AProject management plan
  • BTeam performance assessment
  • CProject staff assignment
  • DResource calendar

How the community answered

(41 responses)
  • A
    78% (32)
  • B
    22% (9)

Community Discussion

No community discussion yet for this question.