GIAC
GCPM · Question #750
You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased…
The correct answer is B. Make-or-Buy Analysis. See the full explanation below for the reasoning.
Question
You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?
Options
- AContract Types
- BMake-or-Buy Analysis
- CProcurement Negotiations
- DExpert Judgment
How the community answered
(39 responses)- A5% (2)
- B72% (28)
- C15% (6)
- D8% (3)
Community Discussion