Question

The Project Manager is ordering cables for the video board he is developing. He can only order these cables from one company that has a patent on the design. Which of the following describes the type of procurement he is performing?

Options

  • ASole source
  • BOpen source
  • CSource selection
  • DQualified sellers list

How the community answered

(55 responses)
  • A
    76% (42)
  • B
    13% (7)
  • C
    4% (2)
  • D
    7% (4)