GCPM · Question #7
Which of the following is described in the statement below? "It is a tool that defines a project and groups the project's discrete work elements in a way that helps organize and define the total…
The correct answer is A. WBS. See the full explanation below for the reasoning.
Question
Which of the following is described in the statement below? "It is a tool that defines a project and groups the project's discrete work elements in a way that helps organize and define the total work scope of the project."
Options
- AWBS
- BRBS
- CGantt chart
- DCritical path
How the community answered
(37 responses)- A84% (31)
- B3% (1)
- C5% (2)
- D8% (3)