GCPM · Question #64

Which of the following techniques is described in the statement below? "It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid of any…

The correct answer is C. Critical path method. See the full explanation below for the reasoning.

Question

Which of the following techniques is described in the statement below? "It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid of any resource limitations by performing a forward and backward pass analysis through the schedule network."

Options

  • AResource utilization
  • BResource leveling heuristic
  • CCritical path method
  • DCritical Chain method

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    10% (2)
  • C
    76% (16)
  • D
    10% (2)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice