nerdexam
GIAC

GCPM · Question #48

the risk responses. Your project has a budget of $450,000 and is expected to last seven months. You have identified a risk event that has a probability of .60 and has a cost impact of $250,000…

The correct answer is B. Risk exposure is $150,000. See the full explanation below for the reasoning.

Question

the risk responses. Your project has a budget of $450,000 and is expected to last seven months. You have identified a risk event that has a probability of .60 and has a cost impact of $250,000 within the project. While creating a risk response for this event, what is the risk exposure of the event that must be considered for the cost of the risk response?

Options

  • ARisk exposure is $250,000.
  • BRisk exposure is $150,000.
  • CRisk exposure is $350,000.
  • DRisk exposure is $50,000.

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    82% (23)
  • C
    4% (1)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice