GCPM · Question #417
GCPM Question #417: Real Exam Question with Answer & Explanation
The correct answer is B. Cost of Quality. See the full explanation below for the reasoning.
Question
Which of the following is described in the statement below? "It is a monetary calculation of the quality performance of an organization. It is the monetary figure used by project management personnel in the decision making process."
Options
- AScope creep
- BCost of Quality
- CCost benefit analysis
- DIntegrated change control