GCPM · Question #417

GCPM Question #417: Real Exam Question with Answer & Explanation

The correct answer is B. Cost of Quality. See the full explanation below for the reasoning.

Question

Which of the following is described in the statement below? "It is a monetary calculation of the quality performance of an organization. It is the monetary figure used by project management personnel in the decision making process."

Options

  • AScope creep
  • BCost of Quality
  • CCost benefit analysis
  • DIntegrated change control