You are the project manager of the NJYO Project and are working with your project team to create the Work Breakdown Structure (WBS). This project will span all areas of the matrix organization and…
The correct answer is B. The creation of the WBS is an example of team building. See the full explanation below for the reasoning.
Question
You are the project manager of the NJYO Project and are working with your project team to create the Work Breakdown Structure (WBS). This project will span all areas of the matrix organization and your project team doesn't really know the resources from the other departments. Some of the project team members have asked that you excuse them from the WBS when the section of the project scope doesn't apply to them. You tell them 'No'. Why?
Options
- AThe project team should work on the WBS as a whole even if they cannot contribute.
- BThe creation of the WBS is an example of team building.
- CYou need all the project team members to see that you are in charge of this diverse group.
- DIt would not be fair to the other project team members.
How the community answered
(54 responses)- A7% (4)
- B78% (42)
- C13% (7)
- D2% (1)