You, with your team, are performing the work defined in the project management plan to achieve the project's objectives. In which of the following processes are you working on?

The correct answer is D. Direct and Manage Project Execution. See the full explanation below for the reasoning.

Question

You, with your team, are performing the work defined in the project management plan to achieve the project's objectives. In which of the following processes are you working on?

Options

  • APerform Quality Assurance
  • BDevelop Project Team
  • CManage Project Team
  • DDirect and Manage Project Execution

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    4% (1)
  • D
    84% (21)