GCPM · Question #410

Which of the following are outputs of the Acquire Project Team process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is B. Project staff assignments C. Resource calendars D. Project management plan updates. See the full explanation below for the reasoning.

Question

Which of the following are outputs of the Acquire Project Team process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AOrganizational process assets
  • BProject staff assignments
  • CResource calendars
  • DProject management plan updates

How the community answered

(33 responses)
  • A
    21% (7)
  • B
    79% (26)

Community Discussion

No community discussion yet for this question.