What component of the change control process examines the entire project to determine the proposed change's impact on the project scope, time, cost, quality, human resources, communications, risk…

The correct answer is A. Integrated change control. See the full explanation below for the reasoning.

Question

What component of the change control process examines the entire project to determine the proposed change's impact on the project scope, time, cost, quality, human resources, communications, risk, and procurement?

Options

  • AIntegrated change control
  • BScope change control system
  • CConfiguration management
  • DProject management information management system

How the community answered

(27 responses)
  • A
    70% (19)
  • B
    7% (2)
  • C
    4% (1)
  • D
    19% (5)