GIAC
GCPM · Question #404
What component of the change control process examines the entire project to determine the proposed change's impact on the project scope, time, cost, quality, human resources, communications, risk…
The correct answer is A. Integrated change control. See the full explanation below for the reasoning.
Question
What component of the change control process examines the entire project to determine the proposed change's impact on the project scope, time, cost, quality, human resources, communications, risk, and procurement?
Options
- AIntegrated change control
- BScope change control system
- CConfiguration management
- DProject management information management system
How the community answered
(27 responses)- A70% (19)
- B7% (2)
- C4% (1)
- D19% (5)
Community Discussion
No community discussion yet for this question.