GIAC
GCPM · Question #401
Which of the following are the tools and techniques of the Plan Procurements process? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. Contract types B. Expert judgment C. Make-or-buy analysis. See the full explanation below for the reasoning.
Question
Which of the following are the tools and techniques of the Plan Procurements process? Each correct answer represents a complete solution. Choose all that apply.
Options
- AContract types
- BExpert judgment
- CMake-or-buy analysis
- DProbability and impact matrix
How the community answered
(39 responses)- A72% (28)
- D28% (11)
Community Discussion