Which of the following are the tools and techniques of the Plan Procurements process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is A. Contract types B. Expert judgment C. Make-or-buy analysis. See the full explanation below for the reasoning.

Question

Which of the following are the tools and techniques of the Plan Procurements process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AContract types
  • BExpert judgment
  • CMake-or-buy analysis
  • DProbability and impact matrix

How the community answered

(39 responses)
  • A
    72% (28)
  • D
    28% (11)