You are a Project Manager in your organization who is managing a considerably huge budget project to develop new software. Considering the varied nature of your stakeholder group, you would like to…

The correct answer is C. Communications Management Plan, Planning Process Group. See the full explanation below for the reasoning.

Question

You are a Project Manager in your organization who is managing a considerably huge budget project to develop new software. Considering the varied nature of your stakeholder group, you would like to put together a plan as to what information the stakeholders need, and how to provide that information. What is the document that you would need, and as part of which process group would you achieve this?

Options

  • ACommunications Management Plan, Execution Process group
  • BProject Management Plan, Planning Process Group
  • CCommunications Management Plan, Planning Process Group
  • DProject Management Plan, Initiating Process Group

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    14% (4)
  • C
    72% (21)
  • D
    3% (1)