Question
You are the project manager for your organization. The resources that you'll be using on your project are part of a union. The union representatives inform you that you may only utilize union labor on your project for a maximum of 25 hours per week. What approach will you need to do to reveal over utilization of the union resources?
Options
- ACritical path method
- BFast tracking
- CCritical chain method
- DResource leveling