GCPM · Question #383

Which of the following processes is described in the statement below? "It addresses the risks by their priorities, schedules the project management plan as required, and inserts resources and…

The correct answer is C. Plan risk response. See the full explanation below for the reasoning.

Question

Which of the following processes is described in the statement below? "It addresses the risks by their priorities, schedules the project management plan as required, and inserts resources and activities into the budget."

Options

  • ACreate the project risk register
  • BCreate a risk governance approach
  • CPlan risk response
  • DMonitor and control project risks

How the community answered

(31 responses)
  • A
    16% (5)
  • B
    6% (2)
  • C
    74% (23)
  • D
    3% (1)