GCPM · Question #383
Which of the following processes is described in the statement below? "It addresses the risks by their priorities, schedules the project management plan as required, and inserts resources and…
The correct answer is C. Plan risk response. See the full explanation below for the reasoning.
Question
Which of the following processes is described in the statement below? "It addresses the risks by their priorities, schedules the project management plan as required, and inserts resources and activities into the budget."
Options
- ACreate the project risk register
- BCreate a risk governance approach
- CPlan risk response
- DMonitor and control project risks
How the community answered
(31 responses)- A16% (5)
- B6% (2)
- C74% (23)
- D3% (1)