The correct answer is B. Acceptance of the project deliverables. See the full explanation below for the reasoning.
Question
Micha is the project manager for her project. Micha is now ready to complete the scope verification process so that she can move the project into the project closing process. What is the primary purpose of the scope verification process?
Options
- AReview of the project performance
- BAcceptance of the project deliverables
- CAcceptance of the project team's performance
- DApproval that the project has met its objectives
How the community answered
(37 responses)- A3% (1)
- B78% (29)
- C14% (5)
- D5% (2)
Community Discussion