GCPM · Question #376

GCPM Question #376: Real Exam Question with Answer & Explanation

Sign in or unlock GCPM to reveal the answer and full explanation for question #376. The question stem and answer options stay visible for context.

Question

$950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

Options

  • A0.84
  • B0.86
  • C0.98
  • D0.95

Unlock GCPM to see the answer