$950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone. What is the project's cost…
The correct answer is D. 0.95. See the full explanation below for the reasoning.
Question
$950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone. What is the project's cost performance index?
Options
- A0.84
- B0.86
- C0.98
- D0.95
How the community answered
(32 responses)- A3% (1)
- B6% (2)
- C16% (5)
- D75% (24)