nerdexam
GIAC

GCPM · Question #376

$950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone. What is the project's cost…

The correct answer is D. 0.95. See the full explanation below for the reasoning.

Question

$950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

Options

  • A0.84
  • B0.86
  • C0.98
  • D0.95

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    16% (5)
  • D
    75% (24)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice