Which of the following are outputs of the Develop Project Team process? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. Team performance assessment C. Enterprise environmental factors update. See the full explanation below for the reasoning.
Question
Which of the following are outputs of the Develop Project Team process? Each correct answer represents a complete solution. Choose all that apply.
Options
- ATeam performance assessment
- BProject management plan
- CEnterprise environmental factors update
- DProject staff assignment
How the community answered
(34 responses)- A82% (28)
- B6% (2)
- D12% (4)