GIAC
GCPM · Question #37
Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to…
The correct answer is C. Transference. See the full explanation below for the reasoning.
Question
Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?
Options
- AMitigation
- BAcceptance
- CTransference
- DAvoidance
How the community answered
(26 responses)- A8% (2)
- B4% (1)
- C85% (22)
- D4% (1)
Community Discussion
No community discussion yet for this question.