nerdexam
GIAC

GCPM · Question #37

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to…

The correct answer is C. Transference. See the full explanation below for the reasoning.

Question

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?

Options

  • AMitigation
  • BAcceptance
  • CTransference
  • DAvoidance

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    85% (22)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.

Full GCPM Practice