nerdexam
GIAC

GCPM · Question #37

GCPM Question #37: Real Exam Question with Answer & Explanation

Sign in or unlock GCPM to reveal the answer and full explanation for question #37. The question stem and answer options stay visible for context.

Question

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?

Options

  • AMitigation
  • BAcceptance
  • CTransference
  • DAvoidance

Unlock GCPM to see the answer

You've previewed enough free GCPM questions. Unlock GCPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full GCPM Practice